EPIC® Application Methods
How is EPIC® applied?
There are two recommended methods for EPIC® application:
- The Rolling method uses an 18" roller dipped into EPIC® and rolled onto the floor. This method can be performed by one person, and is recommended for first-time applicators and Do-It-Yourself projects. The resulting coat is thicker, yielding less coverage (150-200 square feet per Standard kit, 300-500 square feet per Contractor kit).
- The T-Bar/Back-Roll method requires at least two applicators, one using a T-Bar and at least one more using a 12" or 18" back-roller. EPIC® is poured onto the floor and spread with the T-Bar, then back-rolled. The resulting coat is thinner, yielding more coverage (300-400 square feet per Standard kit, 600-800 square feet per Contractor kit).